TNS Lead Times
The following are general lead times for telecommunications and networking service requests. The lead times are initiated at the time a properly completed and signed Telecommunications Service Request (TSR and supporting documentation (e.g., Design Request Form) are received and when the customer receives an e-mail confirming agreement on the scope of the work and the receipt of a signed TSR. Depending on the nature and complexity of the service request, much of the preliminary design discussions may occur before the confirming email is sent and work is initiated.
Requests that will result in major renovations or require infrastructure or facility upgrades may necessitate longer lead times and will be addressed according to the requirements of the individual project (ex. outside wire/fiber installation). All lead times specified are estimated within normal business days and does not include weekends or holidays.
| Cable TV Service Lead Times |
|
The following lead time assumes available facilities (e.g., wire/fiber). If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor.
|
|
System/Service
|
Parts Available in Inventory
|
Parts Not Available in Inventory
|
|
Cable TV Design & Installation
|
2 - 6 Weeks
|
8 - 12 Weeks
|
|
For more information call (814) 865-5486 or submit an inquiry through the CATV Service Request Form
|
| Cable/Wiring Service Lead
Times |
|
Lead times do not include projects that require coordination with OPP, non-PSU architects, and/or engineers, or other 3rd party contractors.
|
Inside Building
Definitions
-
Jack - A single telecommunications RJ-45, coax or MT-RJ, ST or SC fiber connector.
-
Outlet - A telecommunications physical location consisting of a single or multiple jacks located on a single faceplate.
Lead times assume the following:
-
Lead times BEGIN when all outlet locations have been identified and shown graphically on a plan.
-
Adequate space exists within the serving Telecommunications Room for all required active and passive components and equipment.
|
6 Outlet locations or less |
3 Days |
50 Jacks or less |
3 Weeks |
Over 50 Jacks |
5 Weeks |
Complete Building |
To be determined |
Between Buildings (Inter Building wire/fiber)
Definitions
- Segment - a single pole-to-pole span or a manhole-to-manhole
duct bank section
Lead times assume the following:
- No Right-of-Way agreements are required.
- No pole attachment agreements are required.
- Project involves only University owned property
-
Adequate pathways (either duct bank or aerial) exist. Lead times do not include design for construction of new pathways.
-
Does not include copper telephone wiring. Lead times vary according to how far into the distribution system the design must address to find available pairs.
|
Short Runs (3 Segments or Less) |
4 Weeks |
Other Runs (more than 3 Segments) |
6 Weeks |
|
For more information call (814) 865-6580 or submit an inquiry through the Special Projects Design Request Form
|
| DHCP Service Lead Times |
TNS provides Dynamic Host Configuration
Protocol (DHCP) Service. The DHCP lead time is based on the time a
request is made by an authorized Administrative, Technical or Security
Backbone Contact and a confirmation e-mail is sent by TNS.
|
| Requests for DHCP Service |
3 business days |
|
For more information call (814) 865-5485 or submit an inquiry through the DHCP Information Request Form
|
| Firewall Service Lead Times |
|
The lead times may vary depending on if the system spans within a building or spans multiple buildings and if the appropriate facilities (e.g., wire/fiber) are available. If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor.
|
| System/Service |
| Firewall Design & Installation |
8 - 12 Weeks |
|
For more information call (814) 865-5486 or submit an inquiry through the Firewall Service Request Form
|
| Integrated Backbone (Connection) Service Lead Times |
|
The lead times may vary depending on if the system spans within a building or spans multiple buildings and and if the appropriate facilities (e.g., wire/fiber) are available. If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor.
|
|
System/Service
|
| Integrated Backbone Design & Installation |
8 - 12 Weeks |
|
For more information call (814) 865-6285 or submit an inquiry through the Integrated Backbone Request Form
|
| Local Area Network (LAN) Service Lead Times |
|
The lead times may vary depending on if the system spans within a building or spans multiple buildings and if the appropriate facilities (e.g., wire/fiber) are available. If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor.
|
|
System/Service
|
| New LAN Design & Installation |
8 - 12 Weeks |
| Moves/Changes to LANs under TNS Full Maintenance |
2 - 8 Weeks |
| LAN Expansion: Patch Cable Only for LANs under TNS Full Maintenance |
2 - 8 Weeks |
| LAN Expansion: Additional hardware at the Hub required |
7 - 10 Weeks |
|
For more information call (814) 865-5486 or submit an inquiry through the LAN Service Request Form
|
| Point to Point Circuit Service Lead Times |
|
The lead times may vary depending on if a vendor circuit is required and if the appropriate facilities (e.g., wire/fiber) are available. If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor.
|
|
System/Service
|
| Point to Point Circuit Design & Installation |
4 - 8 Weeks |
|
For more information call (814) 865-6285 or submit an inquiry through the Point to Point Circuit Inquiry Form
|
| Satellite Downlink Service Lead Times |
|
The lead times may vary depending if a contractor is or is not required, availability of parts, and if the appropriate facilities (e.g., wire/fiber) are available. If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor.
|
|
System/Service
|
| Satellite Downlink Design & Installation |
4 - 10 Weeks |
|
For more information call (814) 865-6580 or submit an inquiry through the Special Projects Design Request Form
|
|
Voice System Services Lead Times(VoIP, Centrex, Voice Switching and Voice Messaging)
|
|
The lead times may vary depending if a contractor is or is not required and if the appropriate facilities (e.g., wire/fiber) are available. If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor. The lead times listed below are for 8 or less lines, extensions, or single line sets.
|
|
Centrex/Merlin/Meridian System/Service
|
| Centrex Service - No service contractor work required |
3 - 8 Weeks |
| Centrex Service - Service contractor work required |
4 - 8 Weeks |
| Meridian Business Set Design/Installation/Moves |
4 - 8 Weeks |
| Merlin Changes (New Extensions/Moves) |
4 - 8 Weeks |
|
Voice over IP System/Service
|
| VoIP Design & Installation |
6-18 Weeks |
| VoIP Adds/Moves/Changes |
3 - 4 Weeks |
|
Voice Switching and Messaging/Voice Mails System/Service
|
| Name change, swap similar ports, add area code(s), activate wired ports 5 or less requests |
1 Day |
| Name change, swap similar ports, add area code(s), activate wired ports 5 or more requests |
5 Days |
| No service vendor work required - Non-UP |
3 Days - 3 Weeks |
| No service vendor work required - UP |
1 - 3 Weeks |
| Service vendor work required - UP |
1 - 6 Weeks |
|
For more information call (814) 865-1696 or submit an inquiry through the Voice System Services Inquiry Form
|
| Interactive Video Conference Rooms |
|
The lead times may vary depending if a contractor is or is not required, availability of parts, and if the appropriate facilities (e.g., wire/fiber) are available. If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor.
|
| Interactive Video Conference Room Design & Installation |
4 - 10 Weeks |
|
For more information call (814) 865-1696 or submit an inquiry through the Videoconferencing Room Design Service
|
| Wireless LAN Service |
|
The Wireless LAN Service lead times apply to ITS Complete Wireless designs and installations. The Wireless LAN Service lead times represent two distinct phases of a wireless deployment (1) a wireless RF Design and (2) the actual wireless LAN design and installation.
|
| Wireless RF Design Service Lead Time |
The wireless RF design lead time assumes the following:
-
No existing RF interference in the design frequency range.
-
Adequate space exists within the serving Telecommunications Room for all required active and passive components and equipment.
-
Full access to the spaces for survey work.
-
The desired coverage area has been adequately identified and shown on a plan. Lead times do not include projects that require coordination with OPP non-PSU architects, and/or engineers, or other 3rd party contractors.
|
| Wireless RF Design |
8 Weeks |
| Wireless Complete Design & Installation Service Lead Time |
|
The lead times may vary depending if a contractor is or is not required, availability of parts, and if the appropriate facilities (e.g., wire/fiber) are available. If additional facilities are required these lead times may increase. Lead times begin when the confirming TSR email is sent to the customer/requestor.
|
| Wireless Complete Design & Installation |
8 - 16 Weeks |
|
For more information call (814) 865-6580 or submit an inquiry through the Special Projects Design Request Form
|
|